Client:UNIDO– United Nations for Industrial Development Organisation
Contractor: BEB BioEnergy Berlin
Financed by: UNIDO, CFC (Common Fund for Commodities), TSA (Tanzania Sisal Board) and Katani Ltd
Project time schedule:
Start date: 29. 05. 2006; Hand over: 30. 09. 2007

Content of contract:

  • Turn- key complete project of technical services and supplies
  • Design, engineering and supervisory services
  • Supply of the equipment, materials and spare parts
  • Making available to the training services
  • Erecting, commissioning, testing and start up

Capacity of total digester volume: 2200 m3
Capacity of the CHP-Unit (power generating facility): 360 kW el.